The work also includes handling, salvaging and disposal of cleared material. Clearing and grubbing shall be done well before starting the earthwork operation and in accordance with requirement of project specification. Enumeration of Trees girth more than mm falling within the Toe line shall be prepared and got approved for measurement prior to cut. Modes of measurement shall be done according to clause In case where ground level is less than 0. Also it has to be ensured that the borrow area is being placed in the prescribed zone at the site and also ensure about the soil characteristics of the borrow area like slope, ground water level etc.
Deleterious matters detrimental to the environment shall be disposed off at the designated locations as per direction of the Engineer. Vehicles tracks shall be kept moist to prevent flying of dust particles with the vehicle movement. Nice post. While some small plots of land may be cleared without the help of a professional, larger plots of land may be more difficult to clear without a team of specialists.
This team will often be trained in the fastest and most effective methods of land clearing. They are also more likely to be trained in the local laws and regulations regarding the clearing of land. Remember that land clearing and grubbing is the removal and disposal of all vegetation, rubbish, and surface boulders embedded in the ground. In the total preparation of the site for clear construction, land clearing also includes the removal and disposal of structures, old foundations, and abandoned underground sewers and unused structural concrete of any kind.
Grubbing is the uprooting and removal of roots and stumps. Stripping is the removal and disposal of unwanted topsoil and sod. Clearing, grubbing, and stripping are accomplished by using heavy engineering equipment.
Hand-or power-felling equipment, explosives, and fire are also used. For best results, a combination of methods is used in a sequence of operations. The landowner should remember that land clearing leaves the surface layer of topsoil open to the elements and erosion. If the site is to be left for any great length of time before a project is commenced, this top layer of dirt can be preserved by planting grass in this soil.
While the grass may not be needed on the entire lot, it can be easier to remove a patch of grass for development than to import new dirt, to prevent soil loss. Clearing live trees, dead trees, shrubs and removing damaged storm water drains is all part of our land clearing services.